Project Details
CountryEstonia
LocationPaldiski, Harju
Terminal TypeRegasification (Import)
Rig TypeFSRU
Capacity1.8 mtpa / 2.4 bcm
Trains-
Start Date01-Jan-2025
Cost (US$bn)0.5
Origin-
Destination-
OwnersAlexela {Estonia}
Buyers-
Status Notes
September 2025 - The project is under construction; June 2023 - The project does not have an operating permit yet; December 2022 - The gas pipeline connection built by Elering, a connecting pipeline to the terminal is ready to receive gas; June 2022 - Connecto AS has started construction of the pipeline connection for the terminal
Last reviewed: 13 Jan 2026