Alexandroupolis LNG

Operational

Project Details

CountryGreece
LocationAegean Sea
Terminal TypeRegasification (Import)
Rig TypeFSRU
Capacity4.1 mtpa / 5.5 bcm
Trains-
Start Date01-Jan-2024
Cost (US$bn)0.38
OriginEgypt, United States
Destination-
OwnersGastrade SA [Operator] {Bulgaria}
Buyers-

Status Notes

January 2026 - The terminal received sixth US LNG cargo; October 2024 - The terminal has commenced commercial operations; July 2022 - The terminal is under construction; In June 2021, The European Commission has approved a USD199mn support measure to build the terminal; Gastrade is owned by DESFA (20%), DEPA (20%), Copelouzos Group (20%), Bulgartransgaz (20%) and GasLog (20%); Project Cost - EUR363.7mn

Last reviewed: 23 Jan 2026