Project Details
CountryJapan
LocationFukuoka
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity2.4 mtpa / 3.3 bcm
Trains-
Start Date01-Jan-2014
Cost (US$bn)0.44
OriginMalaysia, Russia
Destination-
OwnersSaibu Gas [Operator] {Japan}, Kyushu Electric Power {Japan}
Buyers-
Status Notes
November 2025 - The terminal started operations in 2014; As per April 2021, Saibu Gas and Kyushu Electric Power Co., Inc. will start studying joint development of an LNG thermal power plant adjacent to the terminal, which aims to start operation in 2025; Project Cost - JPY66bn
Last reviewed: 30 Jan 2026