← Back to Projects

MLNG (Train 9)

Operational

Project Details

CountryMalaysia
LocationBintulu, Sarawak
Terminal TypeLiquefaction (Export)
Rig TypeOnshore
Capacity3.6 mtpa / 4.9 bcm
Trains1
Start Date01-Jan-2016
Cost (US$bn)-
Origin-
Destination-
OwnersENEOS Holdings, Inc. {Japan}, PTT Public Company Ltd {Thailand}, Sarawak State Government {Malaysia}, Petronas [Operator] {Malaysia}
BuyersHokuriku Electric Power Company {Japan}, Hokkaido Electric Power Company {Japan}

Status Notes

October 2023 - Project is operated by Petronas LNG Sdn Bhd; March 2023 - During 2022, Petronas has delivered 405 LNG cargoes from the Bintulu LNG complex, which includes MLNG Satu, MLNG Dua and MLNG Tiga terminals; July 2022 - PTTEP also jointly invests with PTT in the terminal

Last reviewed: 08 Feb 2024