Pluto Train 2

Under construction

Project Details

CountryAustralia
LocationWestern Australia
Terminal TypeLiquefaction (Export)
Rig TypeOnshore
Capacity5 mtpa / 6.8 bcm
Trains1
Start Date01-Jan-2026
Cost (US$bn)5.6
Origin-
Destination-
OwnersWoodside Energy Group Ltd [Operator] {Australia}, Global Infrastructure Partners (GIP) {United States}
Buyers-

Status Notes

December 2025 - Woodside Energy Group Ltd operates the project; July 2024 - Project is 67% complete; August 2022 - Woodside Energy Group Ltd and Bechtel have commenced construction at the project; January 2022 - Woodside Energy Group Ltd has completed the sale of a 49% interest in the terminal to Global Infrastructure Partners (GIP); Final investment decision for the project has been taken in November 2021