← Back to Projects

Port Kembla

Under construction

Project Details

CountryAustralia
LocationPort Kembla, New South Wales
Terminal TypeRegasification (Import)
Rig TypeFSRU
Capacity2 mtpa / 2.7 bcm
Trains-
Start Date01-Jan-2027
Cost (US$bn)0.18
Origin-
Destination-
OwnersSquadron Energy [Operator] {Australia}
Buyers-

Status Notes

December 2025 - Squadron Energy has selected Reganosa Servicios to operate and maintain the terminal at the project; January 2025 - Squadron Energy has completed construction of the project; May 2022 - Squadron Energy has begun construction of the terminal; In November 2021, Squadron Energy has signed a long-term charterparty agreement with Hoegh LNG to supply a floating storage and regasification unit for the terminal; Squadron Energy has signed a 25 - year lease with New South Wales Ports in November 2020; Squadron Energy has acquired JERA's 19.9% and Marubeni Corp's 30.1% interest in the project in October 2020; Project Cost - AUD250mn

Last reviewed: 06 Jan 2026