Project Details
CountryCanada
LocationRichmond County, Nova Scotia
Terminal TypeLiquefaction (Export)
Rig TypeOnshore
Capacity12 mtpa / 16.3 bcm
Trains-
Start Date-
Cost (US$bn)4
Origin-
Destination-
OwnersBuckeye Alternative Energy Solutions Infrastructure LLC {Australia}
Buyers-
Status Notes
November 2023 - Bear Head Energy began to transition the project from LNG to production of low carbon hydrogen and ammonia in 2021; April 2023 - Bear Head Energy has received environmental assessment approval to develop green hydrogen and ammonia production facility instead of the LNG terminal; July 2022 - Buckeye Partners LP has completed the acquisition of Bear Head Energy, which owns the terminal; Project Cost - CAD5bn
Last reviewed: 19 Jan 2024