Project Details
CountryChile
LocationTalcahuano, Bio Bio
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity0.4 mtpa / 0.5 bcm
Trains-
Start Date-
Cost (US$bn)0.1
Origin-
Destination-
OwnersCap {United Kingdom}, Enel {Italy}
Buyers-
Status Notes
As per December 2020, The CAP informed the Environmental Assessment Service of the withdrawal of the project; As per March 2020, Developers have asked Chile's environmental evaluation service SEA to consider their plans, which involve modifying infrastructure belonging to CAP's Huachipato steel division
Last reviewed: 26 Jul 2025