Longkou (PipeChina) LNG

Under constructionChina (Mainland)·Regasification (Import)

Project Details

CountryChina (Mainland)
LocationShandong
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity20 mtpa / 27.2 bcm
Trains
Start Date01-Jan-2026
Cost (US$bn)
Origin
Destination
OwnersChina Oil & Gas Pipeline Network Corp. [Operator] {China (Mainland)}, Nanshan Group Co Ltd {China (Mainland)}
Buyers

Status Notes

June 2026 - The project is expected to commence commercial operations in October; December 2024 - China Oil & Gas Pipeline Network Corp. has completed the interim acceptance inspection for phase I of the project; China Oil & Gas Pipeline Network Corp. (PipeChina) has started construction on terminal in May 2020; The terminal will be build in two phases, of which capacity of 5mntpa will be added in first phase while second phase will increase capacity to 20mntpa