Project Details
CountryCanada
LocationGuysborough County, Nova Scotia
Terminal TypeLiquefaction (Export)
Rig TypeOnshore
Capacity10 mtpa / 13.6 bcm
Trains2
Start Date-
Cost (US$bn)7.6
Origin-
Destination-
Owners-
BuyersUniper {Germany}
Status Notes
November 2025 - The project was cancelled; September 2024 - Simply Blue Group plans to turn the Goldboro site into the location for its major sustainable aviation fuels (SAF) hub; April 2024 - The project is abandoned and Pieridae Energy Ltd. is trying to sell its stake in the project; November 2023 - Pieridae Energy Ltd. has initiated a process to sell its Goldboro subsidiary and associated assets, licenses and permits; April 2023 - The project is still in proposed phase; Project Cost - CAD10bn
Last reviewed: 09 Jan 2026