LNG Canada

Operational

Project Details

CountryCanada
LocationKitimat, British Columbia
Terminal TypeLiquefaction (Export)
Rig TypeOnshore
Capacity14 mtpa / 19 bcm
Trains2
Start Date01-Jan-2025
Cost (US$bn)14.4
Origin-
DestinationJapan
OwnersShell plc {United Kingdom}, Petronas {Malaysia}, PetroChina {China}, Mitsubishi Corporation {Japan}, Korea Gas (Kogas) {South Korea}
BuyersKorea Gas (Kogas) {South Korea}, Vitol {Switzerland}, Tokyo Gas {Japan}, Toho Gas {Japan}

Status Notes

November 2025 - The project is operational; July 2025 - Petronas has shipped its first LNG cargo from the project; December 2023 - The project's construction is more than 85% complete; AkzoNobel is supplying customised protective coatings solutions for under construction facility in July 2020; Project Cost - CAD18bn