Project Details
CountryBelgium
LocationZeebrugge, Bruges, Flemish
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity4.7 mtpa / 6.4 bcm
Trains-
Start Date01-Jan-2024
Cost (US$bn)-
Origin-
Destination-
OwnersFluxys SA [Operator] {Belgium}
Buyers-
Status Notes
July 2025 - The project is operational; June 2024 - Fluxys SA has increased the capacity of the terminal by 4.7 mntpa; April 2023 - The project is currently under construction with 70% completion of pipeline installation across all zones; February 2021 - Fluxys has taken FID for additional regasification capacity at the terminal; The expansion will increase the capacity of the terminal by 4.7 mntpa
Last reviewed: 26 Jul 2025