Project Details
CountryIndia
LocationGujarat
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity2.5 mtpa / 3.4 bcm
Trains-
Start Date01-Jan-2026
Cost (US$bn)-
Origin-
Destination-
OwnersPetronet LNG [Operator] {India}
Buyers-
Status Notes
January 2026 - Oil and Natural Gas Corporation (ONGC) has signed a master regasification agreement with Petronet LNG to enable spot LNG cargo unloading and regasification at the terminal; July 2022 - Petronet LNG has commenced construction activities for the tanks at the terminal in September 2021; As per June 2021, The terminal capacity will be expanded to 22.5mntpa
Last reviewed: 02 Feb 2026