Gopalpur LNG
Under constructionIndia·Regasification (Import)
Project Details
CountryIndia
LocationOdisha
Terminal TypeRegasification (Import)
Rig TypeFSRU
Capacity5 mtpa / 6.8 bcm
Trains—
Start Date01-Jan-2028
Cost (US$bn)0.4
Origin—
Destination—
OwnersPetronet LNG {India}
Buyers—
Status Notes
July 2026 - The project has a capacity of 5mntpa; April 2025 - Petronet LNG has signed an MoU with the Odisha government to develop a land-based LNG terminal at Gopalpur Port; May 2023 - Petronet LNG will go for a land based terminal in case they are unable to procure FSRU for the project; December 2022 - Petronet LNG has accorded investment approval for setting up the terminal in November 2022; Project Cost - INR33bn
Last reviewed: 17 Jul 2026