Projects

Quintero LNG (Expansion Phase II)

CancelledChile·Regasification (Import)

Project Details

CountryChile
LocationValparaiso
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity1.4 mtpa / 1.8 bcm
Trains
Start Date
Cost (US$bn)0.3
Origin
Destination
OwnersFluxys SA {Belgium}, EIG Global Energy Partners LLC {United States}, ENAP - Empresa Nacional del Petroleo {Chile}
Buyers

Status Notes

July 2026 - The project is owned by Fluxys; July 2022 - Enagas and OMERS Infrastructure have closed the joint sale of their 80% stakes in the terminal to a consortium formed by EIG and Fluxys; As per May 2017, The project has been derailed after the sole remaining participant signed a long-term supply deal with one of the incumbent offtakers; The project is operated by GNL Quintero S.A.