Project Details
CountryVietnam
LocationThai Binh
Terminal TypeRegasification (Import)
Rig TypeFSRU
Capacity0.5 mtpa / 0.7 bcm
Trains-
Start Date01-Jan-2030
Cost (US$bn)2
Origin-
Destination-
OwnersCong ty Co phan Tap doan Truong Thanh Viet Nam {Vietnam}, Kyushu Electric Power {Japan}, Tokyo Gas {Japan}
Buyers-
Status Notes
January 2025 - The project aims to complete its feasibility study in Q225 and to begin construction in Q425; January 2024 - Tokyo Gas, Kyuden International Corporation and Truong Tan Vietnam Group have established a joint venture to develop, construct and operate a floating LNG import terminal and a natural gas-fired power plant
Last reviewed: 12 Feb 2025