Dalian LNG
OperationalChina (Mainland)·Regasification (Import)
Project Details
CountryChina (Mainland)
LocationLiaoning
Terminal TypeRegasification (Import)
Rig TypeOnshore
Capacity3 mtpa / 4.1 bcm
Trains—
Start Date01-Jan-2011
Cost (US$bn)1.07
OriginAustralia, Iran, Qatar, Russia
Destination—
OwnersChina Oil & Gas Pipeline Network Corp. [Operator] {China (Mainland)}, Dalian Construction Investment Group Co. Ltd {China (Mainland)}, Dalian Port Corporation Limited {China (Mainland)}
Buyers—
Status Notes
July 2026 - The project is owned by China Oil & Gas Pipeline Network Corp.; December 2025 - SEA SPIRIT vessel berthed at the project; June 2022 - The terminal has applied for re-export permission; China Oil & Gas Pipeline Network Corp. (PipeChina) has acquired a 75% interest in the project from PetroChina in December 2020; Project Cost - CNY7.5bn
Last reviewed: 10 Jul 2026